implementation
- Engineering Design and Implementation
- Mechanical Systems
- Lighting
- On-site Generation: Cogeneration (CHP)
- Renewable Energy: Solar PV
- Resiliency
- Project Construction Management
- Commissioning
- Rebates & Financing
- learn more about our services
Details
- Square Footage: 429,000
- Building Type: Cooperative
- Units: 424
- Year Built: 1965
- Location: Forest Hills, Queens
Through engineering and financial analysis, our engineers recommended and ultimately designed and project managed the following measures for Phase I of the retrofit: Converting the heating plant from oil #6 to lower cost, cleaner natural gas, eliminating summer boiler steam production by installing a direct-fired chiller, installing dedicated domestic hot water (DHW) heaters, installing high efficiency pump motors as well as variable frequency drives (VFDs) on pump and fan motors, and upgrading all interior and exterior lighting. These improvements reduced the Fairview’s source energy use by 23% and allowed the facility to save $333,000 annually. Moreover, EN-POWER GROUP secured $466,000 in grants from NYSERDA, which helped the project achieve a lifetime return on investment (ROI) of 68%.
As a result of Superstorm Sandy, the Fairview decided to protect itself during future extreme weather events by integrating resiliency planning into its building infrastructure – which was of special concern as the building sits within a floodplain. Based on detailed load calculations, EN-POWER GROUP engineers installed an 82-kW solar photovoltaic (PV) system along with a 300-kW cogeneration system for Phase II of the retrofit. Cogeneration, also known as “combined heat and power (CHP)”, is a technology that generates electricity on‑site while also recovering the thermal energy‑byproduct for other uses. Not only is this an extremely efficient process, but CHP also acts as an emergency generator to provide power to essential building systems during power outages. These resiliency improvements generate 1.5 million kWh annually to save the Fairview $170,000 each year. Again, EN-POWER GROUP secured rebate funding from NYSERDA, this time totaling $561,000.
Project Achievements
Phase I
- 23,600 MMBTU
Total Annual Energy Savings - $333,000
Annual Cost Savings - $466,000
Total NYSERDA Rebates - $1,580,000
Total Project Cost after Rebates
Phase II
- 1,476,000 kWh
Total Annual Generation - $561,000
Total NYSERDA Rebates - $170,000
Annual Energy Cost Savings - $1,068,000
Total Project Cost after Rebates
Project Highlights
Phase I
Source energy reduction of 23% & $333,000 in annual energy savings
Phase II
Integration of solar and CHP with one another and into existing systems, green leadership, and $170,000 in annual energy savings
Related Projects
Custom Solutions For Your Building's Complex Energy Needs
To support New York City’s ambitious goal of achieving carbon neutrality by 2025, Municipal Courts have enacted local laws that impose significant financial.