implementation

  • Engineering Design and Implementation
  • Mechanical Systems
  • Lighting
  • On-site Generation: Cogeneration (CHP)
  • Renewable Energy: Solar PV
  • Resiliency
  • Project Construction Management
  • Commissioning
  • Rebates & Financing
  • learn more about our services

Details

  • Square Footage: 429,000
  • Building Type: Cooperative
  • Units: 424
  • Year Built: 1965
  • Location: Forest Hills, Queens

Through engineering and financial analysis, our engineers recommended and ultimately designed and project managed the following measures for Phase I of the retrofit: Converting the heating plant from oil #6 to lower cost, cleaner natural gas, eliminating summer boiler steam production by installing a direct-fired chiller, installing dedicated domestic hot water (DHW) heaters, installing high efficiency pump motors as well as variable frequency drives (VFDs) on pump and fan motors, and upgrading all interior and exterior lighting. These improvements reduced the Fairview’s source energy use by 23% and allowed the facility to save $333,000 annually. Moreover, EN-POWER GROUP secured $466,000 in grants from NYSERDA, which helped the project achieve a lifetime return on investment (ROI) of 68%.

As a result of Superstorm Sandy, the Fairview decided to protect itself during future extreme weather events by integrating resiliency planning into its building infrastructure – which was of special concern as the building sits within a floodplain. Based on detailed load calculations, EN-POWER GROUP engineers installed an 82-kW solar photovoltaic (PV) system along with a 300-kW cogeneration system for Phase II of the retrofit. Cogeneration, also known as “combined heat and power (CHP)”, is a technology that generates electricity on‑site while also recovering the thermal energy‑byproduct for other uses. Not only is this an extremely efficient process, but CHP also acts as an emergency generator to provide power to essential building systems during power outages. These resiliency improvements generate 1.5 million kWh annually to save the Fairview $170,000 each year. Again, EN-POWER GROUP secured rebate funding from NYSERDA, this time totaling $561,000.

Project Achievements

Phase I

  • 23,600 MMBTU
    Total Annual Energy Savings
  • $333,000
    Annual Cost Savings
  • $466,000
    Total NYSERDA Rebates
  • $1,580,000
    Total Project Cost after Rebates

Phase II

  • 1,476,000 kWh
    Total Annual Generation
  • $561,000
    Total NYSERDA Rebates
  • $170,000
    Annual Energy Cost Savings
  • $1,068,000
    Total Project Cost after Rebates

Project Highlights

Phase I

Source energy reduction of 23% & $333,000 in annual energy savings

Phase II

Integration of solar and CHP with one another and into existing systems, green leadership, and $170,000 in annual energy savings

Related Projects

  • Mechanical System Ventilation

Ventilation System Upgrade Improves Indoor Air Quality (IAQ) and Resident Comfort while Saving Energy and Carbon Emissions

  • Controls Building Automation
  • Mechanical Systems Cooling
  • Ventilation

Control System Unlocks $288,000 Rebate for Class A Office Building

  • Commercial
  • Lighting
  • Rebates And Financing

Office Building’s Lighting Upgrade Saves $72,000 and 359,000 kWh Annually

Custom Solutions For Your Building's Complex Energy Needs

To support New York City’s ambitious goal of achieving carbon neutrality by 2025, Municipal Courts have enacted local laws that impose significant financial.