implementation

  • HVAC (Cooling)
  • Energy Auditing
  • Retro-Commissioning
  • Feasibility Study
  • Project Construction Management
  • Controls
  • Rebates & Incentives
  • learn more about our services

Details

  • Square Footage: 132,000
  • Building Style: Luxury Multifamily
  • Units: 149 Residential and 6 Commercial
  • Year Built: 1961
  • Location: West Village,Manhattan

33 Greenwich Avenue, a landmarked cooperative building in Manhattan’s West Village, hired EN-POWER in late 2019 to upgrade its outdated electric screw chiller and cooling tower. Our engineers overcame multiple challenges to successfully replace the equipment on time with a far more efficient electric modular chiller plant and cooling tower, helping improve the building’s energy grade from a “D” to a “C.”

Originally, EN-POWER was hired to conduct its NYC Local Law 87 energy study and retro-commissioning in 2017. Our auditors discovered that the facility’s outdated electric screw chiller and cooling tower both suffered from major performance issues: the cooling tower fan constantly short-cycled (i.e., turned off and on), leading to resident noise complaints and inefficient operation, while the chiller’s performance and reliability had greatly degraded. The chiller’s unreliability was exacerbated by the fact that a single chiller unit was carrying the cooling load of the entire building—meaning when the chiller broke down, residents were left completely without cooling.

As part of the cooling system upgrade, our engineers chose a modular electric chiller because it could provide three critical features: redundancy in case of equipment failure, significantly increased energy efficiency, and minimal on-site construction, as it could be installed in pieces rather than requiring walls to be torn down. We selected high-efficiency motors and variable frequency drives (VFDs) to further reduce energy use. Our team also incorporated both new systems into the site’s existing Building Management System (BMS) to increase ease of operation and reduce client energy costs.

Our engineers overcame multiple challenges to ensure the systems were finished on time in April 2020, including disruptions from COVID-19 lockdowns and securing rigging and permitting approvals from multiple NYC agencies, including the Landmarks Preservation Commission, FDNY, and Department of Buildings, as Essential Construction per COVID Executive Order 202.6. These upgrades helped the building reduce its energy use and carbon footprint. EN-POWER also secured $13,000 in incentives for the project.

Project Achievements

  • 45% (7% Source Savings)
    Cooling Energy Savings
  • 139,400 kWh
    Annual Utility Savings
  • $22,500
    Annual Utility Cost Savings
  • 45 metric tons
    Annual Carbon (CO2) Savings
  • $12,060
    Annual Local Law 97 Penalty Savings
  • $34,560
    Total Annual Savings
  • $747,000
    Total Project Cost with Incentives

Project Highlights

Despite having to navigate multiple NYC agency approvals and the COVID-19 lockdown of April 2020, our engineers successfully replaced the outdated chiller and cooling tower with high-efficiency upgrades that provided cooling redundancy and reduced energy use by nearly 139,400 kWh and the building’s carbon footprint by 45 metric tons annually.

Related Projects

  • Energy Auditing
  • Energy Benchmarking
  • Energy Procurement

Manufacturing Plant Achieved $50,000 in Annual Savings from Energy Efficiency and Procurement Studies

  • Energy Auditing
  • Energy Modeling
  • Feasibility Study
  • Integrated Physical Needs Assessment IPNA

IPNA Study Unlocks Capital Planning Strategies and Funding Opportunities

  • Commercial
  • Lighting
  • Rebates And Financing

Office Building’s Lighting Upgrade Saves $72,000 and 359,000 kWh Annually

Custom Solutions For Your Building's Complex Energy Needs

To support New York City’s ambitious goal of achieving carbon neutrality by 2025, Municipal Courts have enacted local laws that impose significant financial.

    Contact EN-POWER GROUP